News

Daily operation, maintenance and maintenance of automatic cartoning machine

Datetime: 2022-04-13    Visit: 1078



Cartoning machine start-up operation:
1) After confirming that the equipment is normal, turn on the power of the cartoning machine in the distribution carton, turn the power knob of the control cabinet of the cartoning machine to the "on" position, the equipment is powered on, and the alarm light on the equipment control cabinet starts to flash.


2) Turn on the air inlet switch of the equipment. .

3) Press the reset button; if there is an abnormality, the "alarm information" will be displayed on the display screen, and deal with the information according to the prompt; if there is no abnormality, the device can be started.

4) On the touch screen, set parameters such as packaging speed, feeding angle, and photoelectric detection angle according to product characteristics.

5) Put the instruction manual and the small carton code in place according to the production requirements.

6) Press the "Vacuum Pump" button on the touch screen to start the vacuum pump of the equipment. Press the "Paper Open" button on the touch screen to start the compressed air at the origami machine.

7) Press the green "Run" button on the control panel, the equipment will run automatically, put the packaging carton on the conveyor belt, and the automatic packaging can be realized

8) During the adjustment process, when manual cranking is required, first turn off the power of the whole machine, and then use the handwheel to perform manual cranking. If you need to jog, press the "manual operation" - "jog" button after power-on, and the machine can perform jog operation. If you press the "Single Cycle" button, the machine will go through a complete packaging process. If the packaging switch is triggered, the machine also performs a complete packaging action. If film feeding is not required, the film feeding switch can be turned off, and the equipment does not run with film at this time.

9) If there is a fault in the operation of the equipment for maintenance, the tools must be checked, and the crank must be manually turned before starting the equipment to ensure that there are no obstacles in the process of normal operation. Manual cranking: Turn the manual cranking handle to the left and turn the handwheel in the direction of the arrow.

10) The cartoning machine uses manual methods to put the products into the silo. After the equipment starts and runs, the discharging staff puts the materials into the silo to realize automatic packaging. During the discharging process, it is forbidden to stretch your hand to the boat behind the yellow or red and white warning line.


11) After the production is over, press the "Stop" button on the equipment control panel, the equipment will stop running..

Cartoner shutdown operation
1) After the cartoning machine stops running, turn off the "Paper Open" and "Vacuum Pump" buttons on the touch screen in turn.


2) Turn off the air intake opening x< Turn off the power switch on the side of the power distribution carton of the equipment.


3) Turn off the power switch that controls the transparent film packaging machine in the distribution carton on the wall.

Cartoner Maintenance
1) Lubricate the various transmission parts inside the equipment every week, and do not add too much oil to avoid contamination of materials. Each conveyor belt is adjusted every week to ensure that the conveyor belt does not deviate.


2) Remind each other when operating equipment to prevent personnel and equipment accidents caused by misoperation.

3) When cleaning the equipment, it is strictly forbidden for water to enter the electrical parts to avoid electric shock accidents and equipment accidents.

4) When operating the touch screen, you must be careful, you must operate it by hand, and disable other items instead of hand operation to avoid damage.

5) Every week, check whether the screws and transmission parts of the connecting parts of the equipment are loose, and check whether the silo conveyor chain collar falls off.


6) During the operation of the machine, pay attention to whether the machine has abnormal noise and odor, and quickly turn off the power and report for repair.

Cartoner Repair
1) When overhauling the cartoning machine equipment, be sure to cut off the power supply and turn off the compressed air, and make sure that it is correct before overhauling.


2) Check all transmission parts every week to ensure that there is no looseness or abnormality in the transmission parts.

3) Add lubricating oil to all transmission parts in the chassis every week to ensure that the transmission of each part is flexible and no abnormality, and the main shaft and cam transmission parts should be lubricated.

4) Use compressed air to dedust the electrical control carton every month, and fasten all the terminals, wipe the surface of the equipment and electrical appliances with a dry towel, and wipe the inside of the equipment chassis with cotton silk, so that there is no visible dust and dirt on the surface of the equipment, and the equipment appears True color.

5) Check the switch button and emergency stop button every month to ensure that they work normally and effectively.

6) Change the lubricating oil once every 5000 hours of operation of the reducer, specification: hyperbolic gear oil.